fastProject 4.10.1 Released
/General
Fixed setting a Target Date problem when dates are in UK date format (dd/mm/yyyy), where a Target date would default to today if was an invalid US date (e.g. 31/08/2020).
Baselines
Color changed to a light orangey-yellow to make it more visible
Baseline bar for summary tasks now appears above the Summary bar (same as task bar). Note: you will need to update your Views: Tools > Restore > Restore Views
Critical path
Bug fixed where a critical path was not displayed if it started with a Touchpoint task (not a milestone)
Update
Can now import a duration on a non-started task which has the effect of changing the duration in the schedule
Improved the scenario when no tasks are updated. The user is now informed that all tasks are updated to the current date and there is no additional dialog box to “quit” from.
Fixed bug when generating the PreFresh report if the lookahead number of days was greater than a few hundred
Fixed bug where the “Last Update” info returned no results of run on the same day as an update and there were no in-progress tasks
Fixed problem where the number of days to Lookahead in the PreFresh report couldn’t be changed (shortcut added so can just double-click an manually enter a number) a new value
Analyzer
Added “Remove All Deadlines” option under the Negative Float test
Macro-micro Roll-up
Going to a task in the linked schedule now automatically displays the critical path to that task
Fixed bug where a non-started roll-up task that was part of a different schedule got it’s date constraint removed, putting it back to the beginning of the project