fastProject 4.10.4 Released

General

  • Fixed problem where a date stamp for the Notes was not being recorded when an existing file was opened.

Tools

  • Importing a Touchpoint/Checkpoint or Deliverable now:

    • Updates the “Last Updated” date

    • Does not open all tasks prior to importing

  • Added a new function under Summary Years On/Off - Cross-summay Dependency Analysis that shows all dependencies between two selected summary tasks

  • Improved report for generating a task report for Marked tasks, Actions and Notes

Macro-micro Roll-up

  • Improved calculation of negative lags to better align with the micro

  • Fixed problem where a bogus dependency was made during a roll-up if the task was an external task. External tasks are now ignored.

Inspector

  • Fixed problem with finding “All Preds” when a critical path hasn’t been previously determined

Refresh

  • Improved PreFresh report with:

    • New options to show/hide the primary columns/text fields

    • Ability to add up to 6 custom columns selected from any of the remaining 27 custom text fields. All user columns can now be changed and imported when the PreFresh report is imported.

  • Improved Tasks This Week (was the PostFresh report)

  • Wigglechart

    • Simpler coding scheme for weekly change: Green up arrow = pull-in, Yellow dash = no change, Red down arrow = slip

    • Days to pull-in in the Wigglechart now to one decimal place

Report

  • Added Completion group (Text4) to the Focus This Week report

  • Added Completion group (Text4) to the Late Simulator report

  • Updated Tasks This Week report with option to include Wigglets (does not include by default)

  • Bug fixed in the Late Simulator where tasks were not stored by the Days to Pull-in when selected

  • Problem fixed where the WBS Analysis form could not be displayed when another form was open