fastProject 4.10.8 Released
/Update
Max number of tasks in the PreFresh report now 3000
Refresh LAR now ignores roll-up tasks that are not milestones
Problem fixed where the number of days lookahead when generating the LAR was off by 1 day
Problem fixed where entering a remaining duration as “on schedule” where the LAR was generated on a day other than the day before the import would cause a 1-day slip
Wigglechart
Problem fixed where the Gap in the Wigglechart would display fractions of a day (number with a decimal point) if the milestone did not finish at the end of a day, e.g. if the scheduled used fractions of a day in its durations
Analyzer
Contiguous critical path test now valid when it starts with a Checkpoint or a Deliverable milestone
Problem fixed where milestones were added to Summary tasks when the Analyzer flag was set to ignore
Macro-Micro Roll-up
Fixed bug where the “Last Updated” time stamp was not being done on roll-down milestones
Fixed problem where negative lags at the macro level were being incorrectly calculated if the earliest task at the micro level had a Start-to-Start dependency
Fixed bug where importing the next day after generating the report would cause all tasks to be schedule 1 day later than entered
Fixed bug where the Roll up/down once did not perform the roll-up
Inspector
New function added to view the change (# days slip/pull-in) for each task. Most useful when looking at the critical path, the peels, a summary view and reporting. Inspector > Change dropdown > Show Change Since Baseline/Hide Change Since Baseline".
Change wording in Review Targets now displays the same wording as the change in the Inspector
Added notes to the “Review Targets” function, primarily to allow you to quickly review and change the “Cause of change” for each target.
Performing a Critical Path Analysis for all targets now generates all charts in a single file with the option to include the Wigglechart and CP Analysis of the top 5 paths for each
Added a “View cause of change” under the “Add cause of change” which opens the notes without adding a date stamp
Added a “Inactivate” (and “Active”) function which Inactivates/Activates all non-started selected tasks and, if a summary tasks, all non-started subtasks.
Fixed bug with Critical Path Analysis (Advanced) where displaying N critical paths included completed tasks
Report
Targets in Gantt now excludes Targets if excluded in the fastProject Options
Targets Report now excludes Targets if excluded in the fastProject Options
Late simulator now excludes Targets if excluded in the fastProject Options
Setting Deadlines to Target dates now excludes Excluded Targets
Bug fixed where the lookahead information and Remaining Duration in the “Tasks This Week” report were incorrect (thanks Moe!)