fastProject 4.10.8 Released

Update

  • Max number of tasks in the PreFresh report now 3000

  • Refresh LAR now ignores roll-up tasks that are not milestones

  • Problem fixed where the number of days lookahead when generating the LAR was off by 1 day

  • Problem fixed where entering a remaining duration as “on schedule” where the LAR was generated on a day other than the day before the import would cause a 1-day slip

Wigglechart

  • Problem fixed where the Gap in the Wigglechart would display fractions of a day (number with a decimal point) if the milestone did not finish at the end of a day, e.g. if the scheduled used fractions of a day in its durations

Analyzer

  • Contiguous critical path test now valid when it starts with a Checkpoint or a Deliverable milestone

  • Problem fixed where milestones were added to Summary tasks when the Analyzer flag was set to ignore

Macro-Micro Roll-up

  • Fixed bug where the “Last Updated” time stamp was not being done on roll-down milestones

  • Fixed problem where negative lags at the macro level were being incorrectly calculated if the earliest task at the micro level had a Start-to-Start dependency

  • Fixed bug where importing the next day after generating the report would cause all tasks to be schedule 1 day later than entered

  • Fixed bug where the Roll up/down once did not perform the roll-up

Inspector

  • New function added to view the change (# days slip/pull-in) for each task. Most useful when looking at the critical path, the peels, a summary view and reporting. Inspector > Change dropdown > Show Change Since Baseline/Hide Change Since Baseline".

  • Change wording in Review Targets now displays the same wording as the change in the Inspector

  • Added notes to the “Review Targets” function, primarily to allow you to quickly review and change the “Cause of change” for each target.

  • Performing a Critical Path Analysis for all targets now generates all charts in a single file with the option to include the Wigglechart and CP Analysis of the top 5 paths for each

  • Added a “View cause of change” under the “Add cause of change” which opens the notes without adding a date stamp

  • Added a “Inactivate” (and “Active”) function which Inactivates/Activates all non-started selected tasks and, if a summary tasks, all non-started subtasks.

  • Fixed bug with Critical Path Analysis (Advanced) where displaying N critical paths included completed tasks

Report

  • Targets in Gantt now excludes Targets if excluded in the fastProject Options

  • Targets Report now excludes Targets if excluded in the fastProject Options

  • Late simulator now excludes Targets if excluded in the fastProject Options

  • Setting Deadlines to Target dates now excludes Excluded Targets

  • Bug fixed where the lookahead information and Remaining Duration in the “Tasks This Week” report were incorrect (thanks Moe!)