fastProject 4.11.4 Released
/General
New feature where the gap to a Target is now displayed next to the name of the Wiggle milestone. Only displayed when the Critical Path IDs are displayed. Note: a one-time upgrade will take place if the capability is not present in the project file. This may take a few seconds.
Actions
Adding an action now automatically populates placeholders for the action and owner in the correct format.
The action placeholder is automatically highlighted so the user can immediately start typing.
Clicking on the action or owner fields automatically highlights the whole field allowing the user to just start typing.
The user can also quickly move between the two by using the Tab key.
Exporting Actions now only exports the actions (and not the whole task’s notes)
Can now Mark and Unmark multiple tasks as actions
Forms that appeared in the top right now now positions the form so the whole form is visible
Added a “Find Missing Activity Owners” function under TOOLS > Tidy Up
Clarifies Add/Update Prefix includes Fill Down when on a column other than the Name column
CP ID column is now automatically hidden when the:
Incomplete tasks is invoked
Wigglechart is run
When importing a schedule, the project calendar is now reset to the default MS Project calendar:
Week starts on Monday
Start/Finish time = 8:00 AM to 5:00 PM
Hours/day = 8, Hours per week = 40, Days per month = 20
Working time = 8:00 AM-12:00 PM, 1:00 PM-5:00 PM (8 hours)
Change Holidays/Working Time made more interactive. Apart from Holidays, there is now no need to click the Set button to record the Working/Non-working/Default days. Dropdowns changed so can’t be edited.
Non-days task durations are now correctly converted when either converting an existing schedule, running the Analyzer of doing a “Tidy Up”. Conversion now takes into account “e”-type durations, task calendars and lag types on the dependencies.
Fixed problem with the breakdown where the milestone wasn’t automatically named correctly if the task task a prefix
Fixed Breakdown of a task that was previously reverted to a single task, where the first duration was 180d.
Fixed problem when running the Analyzer of Tidy Up, where a rescheduled (not started) task would get it’s date constraint removed if the current day was a holiday (so was rescheduled to the next work day in the future).
Update
The last folder selected when importing Update Reports is now stored and used as the default folder the next time the import function is invoked (huge time saver)
Multiple Update Reports can now be imported
Update Reports are imported automatically if no errors are found (no prompt)
Only Update Reports with errors are displayed automatically (and must be saved after changing)
Notes in the Update Report now appears to the right of the Update entry fields
Fixed bug where canceling out of the file select dialog box when importing Update Reports resulted in an unfriendly error
Fixed problem where the initial Update Progress window could appear off screen
Fixed problem where importing only updated tasks where a Remaining Duration was in date format would cause an incorrect error in the Update Report.
Macro-Micro Rollup
Improvements in aligning the macro tasks when rolled-up from the micro, including reflecting the dependency types and lags
Removed non-needed date constraints on the initial creation of the network logic
Analyzer
Touchpoints/Checkpoints/Deliverables with a date constraint in the future are now flagged as an error if they have a predecessor(s)
A check is now made on the default working time. If found to be not 8 hours/day, the user is prompted to reset it to the default 8 hours/day.
NOTE: fastProject only works on an 8 hours/day working day, so the user must change the default working time to 8 hours/day, otherwise all durations may get changed automatically, and not reflect the intended duration.
Reports
Can now customize the long duration of the WBS Analysis (still 30 days be default)
Quick WBS Analysis of near-term tasks > 15 days changed to near-0term tasks > 1 month (30 days)
Documentation
Latest dashboard added to S-Phone Wigglechart.xltm used in the Training class