fastProject 4.9.1 Released

General

  • Filter Task/Filter 2 Tasks fixed

  • New filter added to filter on all incomplete tasks within a date range and no summaries

  • Modified unique code generation when requisition a license to avoid hidden characters

Update

  • New (simpler and faster) PreFresh report along with a new improved (faster) PreFresh import (both default default and advanced)

  • Improved LAR formatting when uploaded to Google Docs

  • Added new function/filter in sub-menu: “Show tasks updated on”

  • Fixed bug where the Start date of tasks with their Touchpoint flag set would get moved to their Finish date

Macro-Micro Roll-up

  • Fixed bug where the roll-up dates of a Summary task in the micro schedule were being reported as not matching with the macro due to a Target in the Summary task (specifically, when the Target was later than the finish date of the Summary)

  • Fixed similar bug when the Target date was earlier than the start date of any subtask, and thus reported an incorrect start date of the roll-up summary task

  • Fixed bug where the update date wasn’t recorded in the macro under some circumstances

  • Fixed bug where the update date wasn’t updated in the micro

Wigglechart

  • Spurious Black dots on the Wigglechart fixed

Analyzer

  • Trend Analysis now extended to all tasks and can be based on a partial part of the task name

  • Fixed problem where tasks exceeded from analysis were reported as errors for the tests Summary No Milestone and Skips End Milestone.

  • Fixed bug where Roll-down touchpoints on tasks had their date changed by the schedule clean-up function, which ended up moving the start date of the task out to the Touchpoint date

Inspector

  • Brand new Critical Path Analysis chart

  • Added ability to do a late report for All Targets in the schedule

  • Late Report:

    • Now includes both Late Start and Late Finish - the Split Bar now snaps so all columns are displayed

    • Fixed bug where all tasks were not displayed if the near-term critical paths mode was set

  • Fixed problem in the Critical Path Analysis chart where an incorrect Target could be displayed if the Wiggle milestone had Subprojects as a predecessor task.

  • Fixed problem with the “Select Target” pop up box opening up when the number of targets is more that the max number of targets (currently set at 40)